Baker Street works

Share on Facebook Share on Twitter Share on Linkedin Email this link
Baker Street works

Transport for London (TfL) owns and manages several properties in Baker Street as well as operational land, the station and railway tracks.

As you may be aware, we undertook investigative works into the state of Baker Street station’s structural underpinnings. During these works, we identified issues that need to be repaired for the long-term safety of the building. To remedy these issues, we have started strengthening, waterproofing and pavement renewal works along 186 – 236 Baker Street as well as along Marylebone Road and part of Allsop Place.

Our remaining programme of works is detailed below. Due to the nature of these works, timescales may be subject to change.

  • 194 - 186 Baker Street and Marylebone Road – December 2023 until April 2024



This page will continue to be updated with the latest information on these works.

Below are some of the questions that we have already been asked, together with answers. If you have any further questions, please contact us directly at bakerstreetworks@tfl.gov.uk.

Q. How long will these works take?

A. These works are scheduled to continue until Spring 2024.


Q. How much disruption will there be to traffic and pedestrians?

A. To minimise disruption, we will work along the street closing sections of pavement where critical works are taking place.


Q. During what hours of operation are the works expected to take place?

A. We will be working between 0800 and 1800 Monday to Friday, although there will be some operational instances where we need to work outside these hours.


Q. Are these works really necessary?

A. Yes. We appreciate that the works may appear unsightly or inconvenient, however their completion is critical for the long-term safety of the buildings on Baker Street.

Transport for London (TfL) owns and manages several properties in Baker Street as well as operational land, the station and railway tracks.

As you may be aware, we undertook investigative works into the state of Baker Street station’s structural underpinnings. During these works, we identified issues that need to be repaired for the long-term safety of the building. To remedy these issues, we have started strengthening, waterproofing and pavement renewal works along 186 – 236 Baker Street as well as along Marylebone Road and part of Allsop Place.

Our remaining programme of works is detailed below. Due to the nature of these works, timescales may be subject to change.

  • 194 - 186 Baker Street and Marylebone Road – December 2023 until April 2024



This page will continue to be updated with the latest information on these works.

Below are some of the questions that we have already been asked, together with answers. If you have any further questions, please contact us directly at bakerstreetworks@tfl.gov.uk.

Q. How long will these works take?

A. These works are scheduled to continue until Spring 2024.


Q. How much disruption will there be to traffic and pedestrians?

A. To minimise disruption, we will work along the street closing sections of pavement where critical works are taking place.


Q. During what hours of operation are the works expected to take place?

A. We will be working between 0800 and 1800 Monday to Friday, although there will be some operational instances where we need to work outside these hours.


Q. Are these works really necessary?

A. Yes. We appreciate that the works may appear unsightly or inconvenient, however their completion is critical for the long-term safety of the buildings on Baker Street.

Page last updated: 18 Mar 2024, 01:00 PM