07 September 2021

Discussion opens

November 2021 → February 2022

Signs and lines work on A107 Clapton Common to Kenworthy Road to 20mph

November 2021 → February 2022

Signs and lines work on A10 – A503 High Road plus Monument Way to 20mph

November 2021 → February 2022

Signs and lines work A13 Commercial Road to 20mph

November 2021 → February 2022

Signs and lines work A23 London Road to 20mph

December 2021 → February 2022

Signs and lines work on A10 Great Cambridge Road to 30mph